LIST OF COMPLETED PROJECT
Project Name |
Allocation & Expenditure (Lakh Tk.) |
Components |
Achievement |
1. Barind Integrated Area Development Project-Phase-I (1985-1990) |
39497.75 & 10411.00 (26.36%) |
a) Installation of DTW (nos.) b) Re-excavation of Ponds (nos.) c) Re-excavation of Canals (miles) d) Water Distribution System (nos.) e) Electrification of DTW (nos.) f) Construction of Feeder Road (km.) g) Aforestation (Lakh) |
1512 1170 6.50 26 10 47.98 49.21 |
2. Barind Integrated Area Development Project-Phase-II (1990-2001) |
49168.00 & 46512.96 (94.60%) |
a) Installation of DTW (nos.) b) Re-excavation of Derelict Ponds (nos.) c) Re-excavation of Canals (km.) d) Construction of Cross dam (nos.) e) Irrigation Water Distribution System (nos.) f) Electrification of DTW (nos.) g) Feeder Road Construction (km.) h) Aforestation (lakh) |
3536 784 40.50 30 2074 3040 65.85 84.21 |
3. Fine Rice Production Project in Barind Area (1995-2001) |
197.00 & 137.52 (69.81%) |
a) Seed Procurement (MT) b) Seed Distribution (MT.) c) Farmers Training (nos.) d) Demonstration plot (nos.) |
43.70 25.65 2679 142 |
4. Rural Drinking Water Supply (PILOT) Project (1995-1997) |
161.50 & 161.50 (100%) |
Drinking Water Distribution System Construction (nos.) |
26 |
5. Barind Rural Road Development Project-Phase-I (1994-2000) |
12600.00 & 12520.10 (99.37%) |
a) Construction of Feeder road (Km) b) Construction of Culvert, Bridge (Nos.) c) Aforestation (Lakh) |
335.38 186 14.15 |
6. Barind Bridging Project (2001-2003) |
2133.00 & 2000.00 (93.76%) |
a) Re-excavation of pond. (Nos.) b) Re-excavation of canal (Km) c) Construction of Cross Dam (Nos) d) Rehabilitation of DTW (Nos.) d) Sapling (lakh) |
80 12.80 8 130 4.00 |
7. Barind Rural Road Development Project-Phase-II (2000-2003) |
1901.00 & 1832.62 (96.40%) |
a) Construction of Feeder road (Km.) b) Construction of Culverts (Nos.) e) Aforestation (Lakh) |
37 22 (162M.) 0.10 |
8. Intensive Aforestation Project (1997-2004) |
958.40 & 957.56 (99.91%) |
a) Aforestation i) Fruit trees (lakh) ii) Forest trees (lakh) |
5.56 21.66 |
9. Repair/Rehabilitation of Deep tube well Project in Greater Dinajpur District Under Post-Drought Agricultural Rehabilitation Programmer (2003-2004) |
1087.83 & 1087.83 (100%) |
Rehabilitation of DTW (Nos) |
1217 |
10. Barind Command Area Development And Training Project of (1996-2006) |
13804.56 & 13804.56 (100%) |
a) Water Distribution System (nos.) b) Farmers training (Person) |
2600 30000 |
11. Barind DTW Electrification Project (1996-2006)
|
14862.70 & 14862.66 (100%) |
a) Electrification of DTW (Nos.) b) Electric Pump purchase (Nos.) c) Construction of sub-station (Nos.) d) Supply & Installation of 3/15 KVA 11/0.4 KV distribution sub-station (Nos.) e) Supply & Installation of 3/10 KVA 11/0.4 KV distribution sub-station (Nos.) f) Rehabilitation of 11/0.04 KV, 3/15 & 3/10 KV distribution sub-station (Nos.) |
2203 2203 5 495
1708
330 |
12. Barind DTW Installation Project (2001-2006) |
13050.00 & 13050.00 (100%) |
a) DTW installation (Nos.)
b) Test well sunk (Nos.) |
1650 Nos (2200 cusec) 100 nos |
13. Bangladesh Fine Rice Production & Marketing Programme (2004-2006) |
250.00 & 98.38 (39.35%) |
a) Training (Person) b) Seed supply and procurement (MT). c) Setting of demonstration Plot (Nos). |
1817 40 70 |
|
14. Eco-System Management in Barind Areas (1999-2006)
|
754.21 &
|
a) Aforestation (lakh sapling) b) Re-excavation of pond (Nos.) c) Re-excavation of canal (Km) d) Cross Dam (Nos.) e) Excavation of Mini ditch. (Nos) f) Water sealed latrine (Nos.) g) Pilot-Home lighting (set) h) Pilot-Biogas plant (Nos.) i) Drinking water supply system j) Established of Eco-village (Nos.) k) Mini Eco-Park (Nos.) |
5.55 43 16.50 11 430 96 23 20 12 9 1 |
|
15. Drinking Water Supply from Irrigation Deep Tubewell Project (2002-2007) |
4124.66 & 4124.53 (100%) |
a) Water supply installation (Nos.) b) Water supply installation extension (Nos.) |
282 27 |
|
16. Command Area Development & Training Project, Unit-2, Thakurgaon (2003-2008) |
9748.50 & 9700.50 (99.51%) |
a) Burried Pipe Line (Nos) b) Water supply installation (Nos.) c) Sprinkler Irrigation system (Nos.) d) Farmers training (Person) |
1217 12 1 12000 |
|
17. Barind Rural Road Development Project, Phase-3 (2003-2008) |
10000.00 & 9999.76 (100%) |
a) Construction of Road (Km.) b) Construction of Bridge/Culvert (Nos.) c) Construction of Office Building (Nos.) d) Road/Culvert repair/maintenance (Km.) e) Aforestation (Lakh.) |
237.50 87 3 686 3 |
|
18. Aforestation Program for Ecological Balance in Unit-2 Area of Barind Project (2005-2008) |
867.69 & 858.26 (98.91%) |
a) Aforestation : i) Fruit tree (lakh) ii) Forest trees (lakh) b) Nursery establishment (Nos.) c) Training (Person) |
3.00 10.00 13 2030 |
|
19. Deep Tubewell Installation Project, Unit-2, Thakurgaon. (2005-2010). |
15995.00 & 15994.61 (100%) |
a) DTW installation (Nos.) b) Electrification of DTW (Nos.) c) Water distribution System (Nos.) d) Training (Person) |
1100 1100 1100 5000 |
|
20. Barind Rain Water Conservation & Irrigation Project. (2004-2010) |
15117.13 & 15116.81 (100%) |
a) Re-Excavation of Canals (Km.) b) Re-Excavation of Derelict Ponds (Nos.) c) Construction of X-Dam (Nos.) |
1000 800 555 |
|
21. Smart Card Based Pre-paid Pump Usage & Energy Measuring System Project. (2008-2010) |
1567.31 & 1567.06 (100%) |
a) Pre-paid Meter (Nos.) b) Smart Card (Nos.) c) Mobile Vending Unit (Nos.) d) Card reader e) Server with necessary equipment f) Tower Installation/construction |
3000 30000 100 25 4 9 |
|
22. Quality Seed Production Project on Farmer Level (2006-2011) |
1032.40 & 1031.77 (99.94%) |
a) Seed production, procurement, processing & marketing (MT) b) Foundation/breeder seed procurement (MT) c) Training (Person) d) Demonstration Plot (nos.) |
2000
65 12600 625 |
|
23. Barind Environmental Balance Restoration Through Afforestation Project (2006-2011) |
2252.43 & 2251.80 (99.97%) |
a) Afforestation (i) Fruit (Lakh) (ii) Medicinal & Forest (Lakh) b) Training (Person) c) Nursery establishment (Nos.) |
16.80 18.70 1042 25 |
|
24. Capacity Building & Resource Mobilization for Sustainable Land Management (Eco System Management) in Bangladesh (SLMP, Barind Part) (2009-2011) |
|
a) Green Manuring (Kg.) b) Compost Heap (Nos.) c) Eco-village (Nos.) d) Plantation (Nos.) e) Water sealed latrine ( nos.) f) Tissue culture lab. (No) g) bio-gas plant (Nos). h) Re-excavation of pond (Nos.) i) Training (Person ) |
1330 20 5 2486 10 1 2 2 75 |
|
25. Barind Integrated Area Development Project-Phase-III (2007-2012) |
28428.00 & 28424.62 (99.99%) |
a) Installation of DTW (nos.) b) Water Distribution System (nos.) c) Electrification of DTW (nos.) d) Aforestation (Lakh) |
2000 2000 2000 0.12 |
|
26. Fine Rice Production & Marketing Programe (2009-2012) |
368.57 & 361.71 (98.14%) |
a) Seed procurement, processing, preservation & marketing (MT) b) Foundation/breeder seed procurement (MT) c) Training (Person) d) Demonstration Plot (nos.) |
416.82
3.27 16000 390 |
|
27. Drinking Water Supply from Irrigation Deep Tubewell Project (2008-2012) |
9302.76 & 9302.26 (99.99%)
|
a) Water supply installation (Nos.) b) Water supply installation extension (Nos.) c) Training (Person) |
695 24 1500 |
|
28. Command Area Development & Training Project, Phase-2 (2008-2013) |
16154.23 & 16123.42 (99.80%) |
a) Burried Pipe Line (Nos) b) Farmers training (Person) |
2500 23500 |
|
29. Command Area Extension & Development Project (2010-2013) |
5124.59 & 5074.06 (99.01%) |
a) Extension of Burried Pipe Line (Nos) b) Rehabilitation of DTW (Nos.) c) Farmers training (Person) |
1000 100 6500 |
|
30. Activating Inoperable DTW for Irrigation Project (2008-2014) |
19913.09 & 19903.32 (99.95%) |
a) Activating Inoperable DTW(Nos.) b) Water Distribution System (nos.) c) Electric line construction (Nos.) d) Pre-paid Meter installation (Nos.) e) Hose/Fita Pipe (Km.) |
2415 2415 2113 400 20 |
|
31. Irrigation programme through surface water augmentation (2013-2016) |
4060.94 & 4060.08 (99.98%) |
a) Re-excavation of Canal (Km.) b) Construction of X-Dam (Nos.) c) Installation of Pontoon (Nos.) d) Installation of LLP (Nos.) e) Water Distribution System (nos.) f) Hose/Fita Pipe (Km.) |
30 7 2 117 117 10 |
|
32. Smart Card Based Pre-paid Pump Usage & Energy Measuring System Project. (2008-2016) |
1908.82 & 1847.68 (96.80%) |
a) Pre-paid Meter (Nos.) b) Smart Card (Nos.) c) Mobile Vending Unit (Nos.) d) Card reader |
4100 82000 160 34 |
|
33. Panchagar, Thakurgaon, Dinajpur and Joypurhat Integrated Area Development Project (2010-2017) |
23225.45 & 23216.35 (99.96%) |
a) Installation of DTW (nos.) b) Water Distribution System (nos.) c) Extension of Burried Pipe Line (Nos) d) Electrification of DTW (nos.) e) Re-excavation of Canal (Km.) f) Re-excavation of Ponds (Nos.) g) Construction of X-Dam (Nos.) h) LLP installation with irrigation chanel i) Aforestation (Lakh) j) Farmers training (Person) |
790 790 725 790 112 11 10 80 8.00 10400 |
34. Deep tubewell Installation project, Phase-ii; (January’2010-June’2018). |
27403.96 & 27400.58 (99.99%) |
a) Installation of DTW (nos.) b) Water Distribution System (nos.) c) Extension of Burried Pipe Line (Nos) d) Electrification of DTW (nos.) e) Re-excavation of Canal (Km.) f) Construction of X-Dam (Nos.) g) LLP installation with irrigation chanel h) Construction of Dugwell (Nos.) i) Irrigation chanel for Dugwell (360 M.) (Nos.) j) Aforestation (Lakh) k) Farmers training (Person) |
1115 1115 1115 1115 40.00 2 25 20 20
0.80 3000 |
35. Marketing agricultural product through development of rural communication project, (October 2010-June 2018). |
33695.69 & 33683.88 (99.96%) |
a) Construction of Feeder Road (Km.) b) Periodic maintenance of constructed road (Km.) c) Construction of culvert (Nos.) d) Aforestation (Lakh) i) Forest 3.14 & ii) Fruits 0.52 |
420 744
108 (382 M.)
3.14 & 0.52 |
36. Barind rain water conservation & irrigation project, Phase-ii; (March-2011-June 2018) |
19999.57 & 19995.87 (99.98%) |
a) Re-excavation of Canal (Km.) b) Re-excavation of pond (Nos.) c) Re-excavation of Dighi (nos.) d) Construction of X-Dam (Nos.) e) Construction of Dugwell (Nos.) f) LLP installation with irrigation chanel g) Soler irrigation system (Nos.) h) Construction of rubber dam (no.) i) Construction of rechargewell (nos.) j) Aforestation (Lakh) i) Forest & ii) Fruits |
600 200 6 97 110 69 46 1 (62 M.) 5 6 & 2 |
37. Rehabilitation of old Deep tubewell in Rajshahi, Chapai-nawabgonj & Naogaon districts; (February’2014-June’2018). |
7724.90 & 7622.57 (98.68%) |
a) Rehabilitation of old DTW (nos.) b) Installation of ground water monitoring Data logger (nos.) c) Construction of electric & buried pipe line (Nos.) |
600 25
400 |
38. Extension of irrigation in Barind area through conservation of water in cannel; (January’2015-June’2018) |
11613.00 & 11612.22 (99.99%) |
a) Re-excavation of Canal (Km.) b) Re-excavation of pond (nos.) c) Construction of X-Dam (nos.) d) Construction of pipe line (M.) e) LLP installation (nos.) f) Installation of solar pump (15 hp) (nos.) g) Aforestation (Lakh) |
38.85 7 16 181000 57 106 0.80 |
39. Drinking Piped Water Supply from Irrigation Deep Tubewells, Phase-iii; (July’2013-June’2018) |
11045.00 & 10698.595 (96.86%)
|
a) Water supply installation (Nos.) b) Water supply installation extension (Nos.) |
550 50 |
40. Enhancement of Irrigation Efficiency Through Construction of Sub-surface Irrigation Channel; (July2015-June2019). |
13616.20 13510.52 (99.22%) |
a) Construction of underground irrigation channel ( km.); b) Farmers training (Person) |
1080
3000 |
41. Extension of irrigation facilities by increasing availability of surface water and removing water logging in Naogaon District; (July 2015-June 2019). |
7912.50 & 7894.60 (99.77%) |
a) Re-excavation of Khal/Khari (Km.) b) Re-excavation of Water body (Acre.) c) Construction of Submerged weir with foot bridge (Nos.) |
92.20 14 13 |
42. Quality Seed Production, Distribution & Farmers’ Training Project for crop production (1st Revised). (July 2015-June 2020) |
1046.23 & 1045.00 (99.88%) |
a) Seed procurement, processing, preservation & marketing (MT) b) Farmer Training (Person) c) Officer Training (Person) d) Demonstration Plot (nos.) e) Field Day (Nos.) |
3000
5000 700 400 100 |
43. Excavation of Dug-well in Barind Area for cultivation of crops by soft Irrigation (Revised-1); (July 2016-June 2021). |
5348.38 & 5347.756 (99.88%) |
a) Excavation of dug-well (Nos.) b) Solar Panel Installation (Nos.) c) 1.5 Inch Dia uPvc Pipe Line construction (360 meter each) (Nos.) |
420 420 420 |
44. Extension of irrigation facilities by augmentation of surface water and mitigation of water logging in Bagha, Charghat & Paba Upazillas of Rajshahi District; (October 2015-June 2021).
|
2987.06 & 2985.26 (99.94%) |
a) RCC Retaining wall b) RCC Slab c) Footover bridge with gatevalve d) Heavy Culvert with gatevalve e) Light Culvert f) Structure for protection of river bank g) Sluice gate h) Re-excavation of Khas Khal/Khari i) Digging of Dug well j) Water distribution system for Dug well k) Water distribution system for LLP |
4035 100 7 2 8 1 1 21.50 20 20 10 |
45. Minor irrigation through pond re-excavation and surface water augmentation; (July,2019 - June,2024). |
14687.50 & 14635.25 (99.65%) |
a) Re-excavation of pond (Nos.) b) Re-excavation of dighi (Nos.) c) Repair of Zonal Office building. (Nos.) d) Construction of uPVC pipeline (Nos.) e) Plantation (Fruit, Forest & Medicinal) (Nos.) f) Construction of Pond Ghat/Steer (Nos.) |
1025 10 10 105 205000
300 |
46. Feasibility Study on "Conservation of Ground Water and Raising Its Use Efficiency and Productivity in Irrigated Agriculture in Bangladesh" (BMDA Part); (July' 2020 - June' 2024.). |
43.92 & 42.292 (96.29%)
|
a) Purchase of UPVC pipes with necessary equipment and installation of pipelines (Meter) b) Outlet structure construction work (Nos.) c) User card(Nos.) |
1200
8 420 |